Thursday, July 18, 2013

Day 30 & Day 31

The framers showed up this afternoon and began organizing the lumber. I'm hoping that we will be under roof by Monday. Whoo!!



Prepping to frame the basement. I'm hoping to be pleasantly surprised after work today. Hopefully I will have a first floor. :D

Day 31: Framing is in full swing!



Lesa being silly :)

Tuesday, July 16, 2013

Day 28 & 29

Yesterday they prepped the basement to get poured. Talked with the PM the basement should be poured today and framing should begin on day 30 or 31 depended on what crew is available first. Not really anything exciting enough to warrant new pictures.

Once the framing starts I the pictures will start coming fast and furious again.

The basement has been poured!



Sunday, July 14, 2013

Day 27

Nothing happened. Hopefully the project gets back on track shortly.

Busy day packing our current home and getting the non-furniture items in to storage. We will be moving out next week and living with my Mom. Time for a beer and some Chinese food!

Saturday, July 13, 2013

Days 23-26

Nothing to report. Several days of rain delayed framing. On top of that it appears that the framers are MIA. Not sure how long we will be in a waiting pattern. I'd had hoped that we would be framed and under roof at this point. How disappointing.

Tuesday, July 9, 2013

Day 21 & 22

Day 21:

The contractors finished up the plumbing rough-ins today. Our yard is still torn up badly but we are closer to framing.

Day 22:

RAIN! How I hate thee. Nothing happening today.

Monday, July 8, 2013

Day 19 & 20

It was a quiet weekend. No work occurred that I could see. The PM told me that the house should be in framing by the end of the week after plumbing is completed.

Friday, July 5, 2013

Day 18 - Wood delivery!

Lou was right on the mark, our wood was delivered today! I manged to get over to the neighborhood as the truck was unloading.



 My daughter near one of our doors and peering through a space in the lumber :)


The crews were hard at work finishing up our plumbing rough ins! Looks like we are ready to start framing. Lou said we should be framing by the end of next week. Probably won't have an update until then!