Day 50

Today the framers came back and finished up. The steps to the bonus room were installed and all of the bulk heads were installed around the plumbing and duct work. There is still some plumbing to finish and electrical to complete before the pre-dry wall meeting happens. The garage door was installed as well.

I talked to my PM and he told me that the house is about 6 weeks from closing at this point.